 Northwest Forcemain Nearing Completion
Mon, Aug 27 2007 The City of St. Augustine new forcemain that is being constructed to accommodate service in the northwest sector of St. Augustine is nearing completion. After successfully acquiring permits for the project, P&A engineers are now on call to troubleshoot concerns, perform site inspections, and provide support to the Contractors and the City Utilities Department. Perhaps the most challenging part of the project, according to P&A field engineer Jesse Colston, has been the directional drilling of the pipe under the San Sebastian river from US 1 on the east side of the river to Helen Street on the west side. The photo shows the end of the pipe on US 1 after it had been drilled under and across the river to Helen Street.
The City of St. Augustine’s sewer forcemain and pump station system that P&A designed in 2006 will serve the special service overlay area that includes Northridge Lakes, Old Sebastian Point and Whispering Creek PUD’s